Mons Orbelus — September Owner Update
Mons Orbelus · Bansko
September Owner Update
Construction progress, fit-out choices and the next deadlines

Dear Archive,

Thank you to everyone who joined our 1 September owners’ meeting. Below is a consolidated update on construction progress, the bathroom and flooring choices discussed, and the actions that need to be completed over the coming weeks.

Please use the Owners Register as the official record of your selections. If you are keeping Standard A, the standard specification will normally proceed automatically unless the category below requires an explicit confirmation.

Open the Owners Register →
Missed the last update? This email builds on our previous project update — if you have not read it yet, some of what follows may not make full sense.

Read the Previous Update →

Join Us
Owners Meeting — Follow-Up Fit-Out Choices
All times are Bansko / Sofia time.
Thursday, 3 September
2026
18:00
Bansko / Sofia time
Zoom Credentials
Meeting ID: 827 7145 2574
Passcode: 520007
Join Zoom Meeting →

If this time does not work for you, please reply to Stela directly or let us know in the owner WhatsApp group — we will follow up with you individually.

To make the most of the meeting, please send Stela any questions arising from this update and the previous one in advance, so we can prepare proper answers rather than working through them live.


Section
Construction Progress
Timing clarification: these dates describe readiness for the next finishing stages. They are not final apartment-completion or handover dates.

Section
How to Confirm Your Choices

Section
Bathroom Choices
Bathroom tiles
Shower divider and shower set
Shower setProductPrice
Standard A—€70 (project value)
Vidima Ceratherm T25 ChromeA7208AA€280
Vidima Ceratherm T25 Silk BlackA7545XG€460

Confirm your shower-set choice by 15 September.

Vanity, mirror and upper cabinet — Category 24 installation support

Lower vanity units and sinks must fit the fixed plumbing and drainage positions. Confirm your choice by 15 September; owner-supplied B2/B3 items must arrive by 10 October.

Installation supportPrice
Mirror installation€60
Upper cabinet without mirror€75
Mirror and cabinet set€110
Vanity with mirror and lights€140 — only where the additional electrical point was requested and prepared

Notify Stela by 15 September if you want installation support.

Toilet, boiler and bathroom heating
Bathroom heatingPrice
Electric towel rail€170 + €30 installation = €200
Quartz radiant heater€30 + €30 installation = €60
Wall-mounted fan heater€55 + €30 installation = €85

Confirm bathroom heating by 20 September.

Bathroom-door opening direction

If you prefer a different bathroom-door opening direction, mark the requested direction clearly on your apartment layout and send it to Stela by 25 September. The site team will accommodate the request where technically possible. Other interior doors follow the project layout.


Section
Underfloor Heating

Section
Laminate and Apartment Flooring

Section
Kitchen Options

The project is working with a custom kitchen manufacturer. Owners may share design ideas with Stela and receive a proposal based as closely as possible on the manufacturer’s catalogue. The process can include onsite measurement, production, installation and warranty, subject to the final quotation.

KitchenPrice
Essential Kitchen€3,300 incl. 20% VAT and €300 installation
Signature Kitchen€3,500 incl. 20% VAT and €300 installation
Premium MDF Kitchen€3,800 incl. 20% VAT and €300 installation

Optional
Complete Furnishing Collections
For owners who would like the apartment fully furnished, not just fitted out.
CollectionPrice incl. 20% VATPositioning
Essential€7,812Entry-level complete furnishing collection
Comfort€9,432Mid-range complete furnishing collection
Premium€12,096Premium complete furnishing collection

The collections include the itemised kitchen, bedroom, living/dining, terrace, lighting and curtain scope shown in the individual quotation. Bathroom vanity furniture and the shower divider are excluded; each total already reflects a €200 reduction. Transport, carrying, assembly, appliance connections, plumbing and electrical installation are quoted separately.


Quick Reference
Deadline Summary
Every date mentioned above, in one place, in order.
DeadlineOwner action
10 SeptemberUnderfloor heating confirmation
13 SeptemberConfirm standard bathroom tile colour or notify the team of custom bathroom tiles
15 SeptemberRemaining bathroom choices; shower set; vanity; boiler; Cat. 24 mirror/upper vanity installation request
20 SeptemberBathroom heating choice; custom bathroom tiles onsite — Floor 1
25 SeptemberBathroom-door direction request; owner-sourced toilet delivery where applicable
30 SeptemberLaminate colour; custom apartment tile map; custom bathroom tiles onsite — Floors 2–3; custom boiler delivery
5 OctoberCustom apartment-floor tiles and applicable skirting materials onsite
10 OctoberCustom bathroom tiles onsite — Floors 4–5; owner-sourced bathroom furniture/heating/shower items onsite

Questions on Any of This?
Reach Out to Stela

For apartment-specific layouts, quotations, custom products or technical questions, please contact Stela. General project updates will continue through the owner email list and WhatsApp group.

Stela, Owner & Fit-Out Coordinator
Stela
Owner & Fit-Out Coordinator · Mons Orbelus
WhatsApp  +359 88 344 3833

Stay in Touch
Owner WhatsApp Group

All project updates go through this email list and the owner WhatsApp group. If you are not yet in the group, join us below — it is the quickest way to stay informed and ask questions directly.

Join the Owner WhatsApp Group →

Thank you for your continued cooperation as the building moves through this important finishing stage.

Uwe
For the Mons Orbelus Team
Mons Orbelus · Bansko, Bulgaria · September Owner Update